Laying marble on screed: what to check

Updated · By Marmi di Carrara srl

How to recognise it / what it is

The problems of a poor installation almost always show in the first months: slabs that sound hollow when tapped with the knuckles, joints that crack, grey or yellowish halos rising from below in light marbles, damp patches that come and go, lips between one slab and the next that you feel barefoot. In some cases the stone lifts or breaks along a line. None of these faults comes from the marble itself: they come from the screed, the adhesive or the timing. That is why laying on screed should be prepared with a few simple checks, before the slabs reach the site.

What causes it

Marble is calcium carbonate, Mohs hardness 3-4, porous and acid-sensitive, with a density of about 2.7 t/m³. A traditional cement screed cures in about 28 days and during that time it shrinks and releases water: if you lay earlier, the residual moisture stays trapped under the stone, forms halos, can dissolve salts and push the slab off. White marbles are slightly translucent: a grey adhesive, or one that yellows through internal reactions, shows through. An incomplete adhesive bed leaves voids that later sound hollow and give way under furniture. Finally marble moves little with temperature, but the screed does: without joints something has to break.

What to do / what NOT to do

Do: wait for the screed to cure and measure residual moisture with a carbide hygrometer or the installer's meter; check flatness with a 2-metre straightedge; use a white cement-based, deformable adhesive suited to natural stone; spread the adhesive in a full bed, with a notched trowel on the screed and on the back of the slab; leave joints of at least 2 mm and movement joints along the perimeter and every 20-25 m². Do not: lay on a screed that is still damp or dusty; use grey or fast-setting adhesives with staining components; lay on "dabs" of adhesive; walk or install furniture before curing; wash with muriatic acid or limescale remover to clear cement residue.

How to prevent it / how to design it well

The floor should be designed together with the screed. Ask the designer which screed is planned, how long it needs before laying and whether there are services underneath. Choose 2 cm slabs for floors: our workshop cuts them to size and numbers them according to the laying plan, so the vein continues from one slab to the next. Allow for a skirting in the same material and a covered perimeter joint. Agree the grout colour with the installer, preferably light on light marbles. Schedule the laying as one of the last jobs, after plastering and services, and protect the floor at once with cardboard and breathable sheets, not with sealed plastic film that traps moisture.

When to call us or an installer/restorer

We supply the material cut to size with the laying plan, and we are happy to talk to your installer about the type of adhesive, the joints and the timing. If a floor is already laid and shows halos from below, hollow-sounding slabs or breaking joints, it needs a site visit by an installer or a restorer: a detached slab can sometimes be replaced and we can supply a matching piece from the same lot, if still available. If the surface has been damaged by acid cleaning, our workshop or a restorer on site can re-polish it. We do not promise that every fault can be fixed: a wrong screed sometimes has to be redone.

The checks before and after laying, step by step

  1. 01Check the age and moisture of the screedAsk for the pouring date: a traditional cement screed needs about 28 days, more if it is thick or if the weather is cold and damp. Have the residual moisture measured with the installer's meter before fixing the laying date.
  2. 02Check flatness and cleanlinessRun a 2-metre straightedge in several directions: lips over 2-3 mm must be levelled first. The screed must be compact, free of dust, oil or plaster residue, or the adhesive will not grip.
  3. 03Choose the right adhesiveFor Bianco Carrara, Statuario, Calacatta and all light marbles you need a white cement-based, deformable adhesive declared for natural stone. Avoid grey adhesives and those that may yellow: they show through translucent marble.
  4. 04Lay in a full bed with jointsTrowel the adhesive onto the screed and the back of the slab, so no voids remain underneath. Leave joints of at least 2 mm, a perimeter joint and movement joints every 20-25 m². Tap every slab down and check with a level.
  5. 05Protect the freshly laid floorDo not walk on it for the time stated by the adhesive manufacturer. Cover with cardboard and breathable sheets during other works, never with sealed film; avoid resting ladders and buckets directly on the stone.
  6. 06First cleaning without acidsGrout residue comes off with lukewarm water, a sponge and neutral detergent, right after grouting. No muriatic acid or limescale remover: they corrode marble in minutes. The protective treatment goes on dry stone only.

Frequently asked questions

How long must the screed wait before laying marble?
For a traditional cement screed normally about 28 days, but what counts is the measured residual moisture, not just the calendar: thick screeds or damp weather may need longer. Fast-setting screeds have their own times stated by the manufacturer.
Why must the adhesive be white?
Light marbles such as Bianco Carrara, Statuario and Calacatta are slightly translucent. A grey or yellowing adhesive can surface as a shadow or halo, and at that point it cannot be removed without lifting the slab.
What thickness is used for a marble floor?
Normally 2 cm, laid in a full bed on a cured, flat screed. Our workshop cuts the slabs to size according to the laying plan; greater thicknesses are only for steps or special requirements.
Can marble be laid without joints?
Not advisable: the screed moves with temperature and moisture and, without a joint of at least 2 mm and perimeter joints, the stress is released onto the stone. A thin, light-coloured joint is almost invisible on white marble.
How is the floor cleaned after laying?
Only with lukewarm water, a sponge and pH-neutral detergent, right after grouting. Never muriatic acid or limescale remover to clear cement residue: they corrode marble. The protective treatment must go on dry stone.